A Great School Deserves a Great Building!
A Great School Deserves a Great Building!
WELCOME TO THE
Matt Kelly Elementary School Replacement Project Page!
We are thrilled to share the journey of transforming Matt Kelly Elementary School into a state-of-the-art learning environment that inspires and empowers our students. Guided by the belief that “A great school deserves a great building,” this project represents our unwavering commitment to building a brighter future for our community.
In collaboration with educators, families, and neighbors, we’re shaping a school that reflects the dreams and aspirations of our students. This replacement project is more than just an upgrade—it’s an investment in the success of current and future generations.
Join us as we dream it, believe it, and achieve it together!
Project Goals and Objectives
Create a modern, safe, and inspiring learning environment
Engage the community in the design process
Preserve the school’s legacy while embracing innovation
Project Timeline
FALL 2024 –
WINTER 2025
Outreach and engagement for input on the design
2025 – EARLY 2026
Architectural designs
MAY 2026
Matt Kelly ES will be closing at the end of May 2026
MAY 2027
Construction complete
Event Photos
Meeting Recap
FAQs
FAQs
What is the expected timeline for the construction project?
- Outreach and engagement for input on the design Fall 2024 – Winter 2025
- Architectural designs 2025 – early 2026
- Matt Kelly ES will be closing at the end of May 2026
- Construction complete by May 2027
What will happen to the students during the 2026 - 2027 school year?
Matt Kelly Elementary School students will be resuming the 2026 – 2027 school year at Ruth Fyfe Elementary School, 4101 W Bonanza Rd, Las Vegas, NV 89107
Will there be any delays in the project, and how will these be communicated to the community?
- Construction is expected to run as expected, however, in the case that the project is going to be delayed we will provide communication via the website: www.sumnumarketing.com/2024/matt-kelly
- Sign up for our newsletter to be notified when there’s an update
Who is the contractor or construction company responsible for the project?
KME Architects is handling the design and partnership with Core Construction
Are there any plans to involve the community in the construction process, such as site tours or informational meetings?
Yes, there were three community meetings held. Between the community meetings we had additional engagement through canvasing to keep the surrounding communities informed. The community meetings were held on: September 19, 2024, October 22, 2024, and February 11, 2025. Since then, we have and continue to engage with the community through tabling at local events.
How will the school keep parents and the community informed about construction progress?
Community engagement meetings, street outreach tems, website and email updates
Is there a website or newsletter dedicated to construction updates?
Yes, for more information please visit www.sumnumarketing.com/2024/matt-kelly
Will there be community meetings to discuss the construction and address concerns?
Absolutely. We already organized and executed 3 community meetings. Read each Meeting Recap Report to learn more.
RSVP: Community Meeting w/ CORE Construction - July 29, 2025
Project Partners
Subscribe To Email Alerts
Project Partners















